Grassroots Satellite LNG Facility

Satellite LNG Facility including storage, vaporization, and truck Unloading

Capacity: 140,000 Gallons Storage, 16 MMSCFD Vaporization

Role: EPC

Year Completed: 2004

A new greenfield LNG peak-shaving facility was needed to provide pressure support to the distribution system in Washington State. The original facility included one 70,000 gallon storage tank and 650 MSCFH vaporization system. CHI also provided design and construction management for a second 70,000 gallon LNG storage tank that was installed two years later.