How long do meter and regulator station projects usually take to complete?

Typically, these engineering projects take less than a year, with an average of eight months. However, the scope of your project will determine the exact timeframe. The design phase can take three to four months and construction can take three to five months. Equipment lead times are critical to the overall schedule.